Boulder

Walnut Street and Mapleton Avenue: The right lane on 30th Street heading northbound has intermittent lane closures. Arrow boards and signage are being used to direct traffic between Walnut and Mapleton. The project is planned to be complete in July.

30th Street and Colorado Avenue: There are right-lane westbound road closures on Colorado as well as for north- and southbound drivers on 30th. The northbound bus stop on 30th is closed. Work occurs from 7 a.m. to 6 p.m. Monday through Friday and is expected to be complete October 2022.

Central Avenue near 57th Court: The pedestrian bridge is closed at Central near 57th Court. An active detour is in place behind traffic barricades in the roadway. There is no set date for reopening the bridge.

Pearl Street: Pearl from Ninth to 11th streets is closed until April.

Pennsylvania Avenue: Pennsylvania from 12th to 13th streets is closed until April.

North Broadway Street: Concrete is being added, and bike lanes are being installed on North Broadway. Vehicle lanes shift to the existing northbound lane and bike lane. The west sidewalk is closed. Construction occurs from 7 a.m. to 5 p.m. weekdays and is expected to be complete in September.

Boulder County

U.S. 287 and Isabelle Road: There are single-lane closures between U.S. 287 and Isabelle from 7 a.m. to 7 p.m. Monday through Saturday.

North 63rd Street: North 63rd Street is reduced to one lane between Jay and Twin Lakes roads so Road Maintenance can safely install steel plates that will reinforce the culvert at the Boulder & Lefthand Ditch. Work will take place between 7 a.m. and 4:30 p.m., Monday through Friday. This work is expected to take two weeks to complete.

Longmont

Fifth and Sixth avenues: Coffman Street will be closed between Fifth and Sixth from Monday to Friday for street reconstruction and paving and striping.

Asphalt/rehab projects with lane shifts and flaggers, the week of Nov. 1

  • 19th Avenue from Francis Street to Main Street.
  • Third Avenue from Main Street to Terry Street.
  • Airport Road from Nelson Road to Rogers Road.
  • Alpine Street from Southwest Homestead Parkway to Northeast Homestead Parkway.
  • Clover Basin Drive from South Fordham Street to Hover Street.
  • East 17th Avenue from Whitehall Drive to County Line Road.
  • Sunset Street from Third Avenue to the BNSF Tracks.
  • South Pratt Parkway Overpass.

Main Street: Will be closed between Third and Longs Peak avenues from 9 to 11:30 a.m. Saturday for the 2021 Halloween Parade. Southbound Main will be detoured at Ninth Avenue; Northbound Main will be available north of Longs Peak Avenue. Longs Peak Avenue will be closed between Pratt and Main streets and Coffman closed between Longs Peak and Eighth avenues during the parade.

Lafayette

120th Street: Traffic on 120th south of the intersection at South Boulder Road is down to single-lane, alternating travel configuration for motorists. A temporary traffic signal will be used to direct traffic. This will be in place 24 hours per day, seven days a week for the next several months. Heavy traffic impacts are expected, and motorists should use alternative routes.

South Boulder Road: The eastern portion of LaMont Does Park parking lot is under construction and is closed. The parking lot on Saratoga Drive will remain open and accessible for overflow parking.

South Boulder Road: The road is in a two-way, head-to-head configuration on the north side of the road. Eastbound and westbound traffic will continue to use this configuration while crews install storm sewer pipe. Motorists can expect minor delays due to buses stopping to pick up and drop off passengers. Motorists can expect to see crews working in the area from 7 a.m. to 6 p.m. Monday through Friday.

Superior

Downtown Superior: The sidewalk on the west side of Superior Drive between Main Street and Old Rail Way is closed for utility work. Pedestrians may use the side on the east side of Superior Drive. Parking on the west side of Superior Drive between Main Street and Old Rail Way is also closed. The construction access road north of Main Street is closed due to the construction of the Marshall Road bridge.

McCaslin Boulevard: Final paving has been completed on McCaslin Boulevard between Coalton Road and Colo. 128. The road is open to traffic, but restoration work and shoulder work will be ongoing until mid-November. Bicyclists are prohibited.

Source by [author_name]

Boulder

Walnut Street and Mapleton Avenue: The right lane on 30th Street heading northbound has intermittent lane closures. Arrow boards and signage are being used to direct traffic between Walnut and Mapleton. The project is planned to be complete in July.

30th Street and Colorado Avenue: There are right-lane westbound road closures on Colorado as well as for north- and southbound drivers on 30th. The northbound bus stop on 30th is closed. Work occurs from 7 a.m. to 6 p.m. Monday through Friday and is expected to be complete October 2022.

Central Avenue near 57th Court: The pedestrian bridge is closed at Central near 57th Court. An active detour is in place behind traffic barricades in the roadway. There is no set date for reopening the bridge.

Pearl Street: Pearl from Ninth to 11th streets is closed until April.

Pennsylvania Avenue: Pennsylvania from 12th to 13th streets is closed until April.

North Broadway Street: Concrete is being added, and bike lanes are being installed on North Broadway. Vehicle lanes shift to the existing northbound lane and bike lane. The west sidewalk is closed. Construction occurs from 7 a.m. to 5 p.m. weekdays and is expected to be complete in September.

Boulder County

U.S. 287 and Isabelle Road: There are single-lane closures between U.S. 287 and Isabelle from 7 a.m. to 7 p.m. Monday through Saturday.

North 63rd Street: North 63rd Street is reduced to one lane between Jay and Twin Lakes roads so Road Maintenance can safely install steel plates that will reinforce the culvert at the Boulder & Lefthand Ditch. Work will take place between 7 a.m. and 4:30 p.m., Monday through Friday. This work is expected to take two weeks to complete.

Longmont

Fifth and Sixth avenues: Coffman Street will be closed between Fifth and Sixth from Monday to Friday for street reconstruction and paving and striping.

Asphalt/rehab projects with lane shifts and flaggers, the week of Nov. 1

  • 19th Avenue from Francis Street to Main Street.
  • Third Avenue from Main Street to Terry Street.
  • Airport Road from Nelson Road to Rogers Road.
  • Alpine Street from Southwest Homestead Parkway to Northeast Homestead Parkway.
  • Clover Basin Drive from South Fordham Street to Hover Street.
  • East 17th Avenue from Whitehall Drive to County Line Road.
  • Sunset Street from Third Avenue to the BNSF Tracks.
  • South Pratt Parkway Overpass.

Main Street: Will be closed between Third and Longs Peak avenues from 9 to 11:30 a.m. Saturday for the 2021 Halloween Parade. Southbound Main will be detoured at Ninth Avenue; Northbound Main will be available north of Longs Peak Avenue. Longs Peak Avenue will be closed between Pratt and Main streets and Coffman closed between Longs Peak and Eighth avenues during the parade.

Lafayette

120th Street: Traffic on 120th south of the intersection at South Boulder Road is down to single-lane, alternating travel configuration for motorists. A temporary traffic signal will be used to direct traffic. This will be in place 24 hours per day, seven days a week for the next several months. Heavy traffic impacts are expected, and motorists should use alternative routes.

South Boulder Road: The eastern portion of LaMont Does Park parking lot is under construction and is closed. The parking lot on Saratoga Drive will remain open and accessible for overflow parking.

South Boulder Road: The road is in a two-way, head-to-head configuration on the north side of the road. Eastbound and westbound traffic will continue to use this configuration while crews install storm sewer pipe. Motorists can expect minor delays due to buses stopping to pick up and drop off passengers. Motorists can expect to see crews working in the area from 7 a.m. to 6 p.m. Monday through Friday.

Superior

Downtown Superior: The sidewalk on the west side of Superior Drive between Main Street and Old Rail Way is closed for utility work. Pedestrians may use the side on the east side of Superior Drive. Parking on the west side of Superior Drive between Main Street and Old Rail Way is also closed. The construction access road north of Main Street is closed due to the construction of the Marshall Road bridge.

McCaslin Boulevard: Final paving has been completed on McCaslin Boulevard between Coalton Road and Colo. 128. The road is open to traffic, but restoration work and shoulder work will be ongoing until mid-November. Bicyclists are prohibited.

, Boulder County cone zones for Oct. 30-Nov. 5 – Boulder Daily Camera , John Fryar , 2021-10-30 17:56:24 , Boulder Daily Camera , https://www.dailycamera.com/wp-content/uploads/2020/08/DCC-L-PIKEROAD_MJ14175.jpg?w=1400px&strip=all , https://www.dailycamera.com/wp-content/uploads/2020/08/DCC-L-PIKEROAD_MJ14175.jpg?w=1024&h=677 , [rule_{ruleNumber}] , [rule_{ruleNumber}_plain] , , , https://www.dailycamera.com/2021/10/30/boulder-county-cone-zones-for-oct-30-nov-5/ , https://www.dailycamera.com/2021/10/30/boulder-county-cone-zones-for-oct-30-nov-5/ , www.dailycamera.com , https%3A%2F%2Fwww.dailycamera.com%2F2021%2F10%2F30%2Fboulder-county-cone-zones-for-oct-30-nov-5%2F , Colorado News,Latest Headlines,Local News,News,Traffic, #Boulder #County #cone #zones #Oct #30Nov #Boulder #Daily #Camera